What are your techniques for reducing unmet hours?

As many of you know programs such as LEED require total hours where the setpoint is not met to be below a certain threshold - e.g. 300 hours. Notwithstanding compliance, I find this to be a best practice for tuning a model. So what techniques do you find are most successful for reducing unmet hours (total, heating, and/or cooling) either in general or for a specific HVAC system? I'm specifically interested in the experiences of EnergyPlus/OpenStudio users.

What are your techniques for reducing unmet hours?

As many of you know programs such as LEED require total hours where the setpoint is not met to be below a certain threshold - e.g. 300 hours. Notwithstanding compliance, I find this to be a best practice for tuning a model. So what techniques do you find are most successful for reducing unmet hours (total, heating, and/or cooling) either in general or for a specific HVAC system? I'm specifically interested in the experiences of EnergyPlus/OpenStudio users.

What are your techniques for reducing unmet hours?

As many of you know programs such as LEED require total hours where the setpoint is not met to be below a certain threshold - e.g. 300 hours. Notwithstanding compliance, I find this to be a best practice for tuning a model. So what techniques do you find are most successful for reducing unmet hours (total, heating, and/or cooling) either in general or for a specific HVAC system? I'm specifically interested in the experiences of EnergyPlus/OpenStudio users.