OpenStudio Year/Week/Day Schedule trouble

I was playing with the Year/Week/Day Schedules in OpenStudio-3.7.0. The following is an example:

OS:ScheduleTypeLimits,
{abaae976-8a76-4786-a0c5-0c4754d162b2}, !- Handle
STL Fraction,                           !- Name
0,                                      !- Lower Limit Value
1,                                      !- Upper Limit Value
Continuous,                             !- Numeric Type
Dimensionless;                          !- Unit Type

OS:Schedule:Day,
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Handle
SD Solar Transmittance - All Days,      !- Name
{abaae976-8a76-4786-a0c5-0c4754d162b2}, !- Schedule Type Limits Name
No,                                     !- Interpolate to Timestep
24,                                     !- Hour 1
0,                                      !- Minute 1
0.15;                                   !- Value Until Time 1

OS:Schedule:Week,
{c729a72e-c91b-43ed-9390-068a3c82c760}, !- Handle
SW Solar Transmittance - All Weeks,     !- Name
,                                       !- Schedule Rendering Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Sunday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Monday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Tuesday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Wednesday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Thursday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Friday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Saturday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Holiday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- SummerDesignDay Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- WinterDesignDay Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- CustomDay1 Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}; !- CustomDay2 Schedule:Day Name

OS:Schedule:Year,
{2dcb64a5-6a91-458b-a136-5e581872632b}, !- Handle
SY Solar Transmittance,                 !- Name
{abaae976-8a76-4786-a0c5-0c4754d162b2}; !- Schedule Type Limits Name

This is embedded in a larger model with many other such schedules, and when I run that model, the following error shows up for all those schedules.

eplusout.err
** Severe  ** ProcessScheduleInput: Schedule:Year="SY SOLAR TRANSMITTANCE" has missing days in its schedule pointers

From what I can tell by the above OS objects, I seem to have all days covered?

Any thoughts would be appreciated.

OOPS, I think there is a part missing from OS:Schedule:Year - I don't have access to that right now, hope I can backfill that tomorrow.

OpenStudio Year/Week/Day Schedule trouble

I was playing with the Year/Week/Day Schedules in OpenStudio-3.7.0. The following is an example:

OS:ScheduleTypeLimits,
{abaae976-8a76-4786-a0c5-0c4754d162b2}, !- Handle
STL Fraction,                           !- Name
0,                                      !- Lower Limit Value
1,                                      !- Upper Limit Value
Continuous,                             !- Numeric Type
Dimensionless;                          !- Unit Type

OS:Schedule:Day,
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Handle
SD Solar Transmittance - All Days,      !- Name
{abaae976-8a76-4786-a0c5-0c4754d162b2}, !- Schedule Type Limits Name
No,                                     !- Interpolate to Timestep
24,                                     !- Hour 1
0,                                      !- Minute 1
0.15;                                   !- Value Until Time 1

OS:Schedule:Week,
{c729a72e-c91b-43ed-9390-068a3c82c760}, !- Handle
SW Solar Transmittance - All Weeks,     !- Name
,                                       !- Schedule Rendering Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Sunday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Monday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Tuesday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Wednesday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Thursday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Friday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Saturday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- Holiday Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- SummerDesignDay Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- WinterDesignDay Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}, !- CustomDay1 Schedule:Day Name
{866e0603-816b-4d3a-8719-712f3e301e60}; !- CustomDay2 Schedule:Day Name

OS:Schedule:Year,
{2dcb64a5-6a91-458b-a136-5e581872632b}, !- Handle
SY Solar Transmittance,                 !- Name
{abaae976-8a76-4786-a0c5-0c4754d162b2}; !- Schedule Type Limits Name

This is embedded in a larger model with many other such schedules, and when I run that model, the following error shows up for all those schedules.

eplusout.err
** Severe  ** ProcessScheduleInput: Schedule:Year="SY SOLAR TRANSMITTANCE" has missing days in its schedule pointers

From what I can tell by the above OS objects, I seem to have all days covered?

Any thoughts would be appreciated.

OOPS, I think there is a part missing from OS:Schedule:Year - I don't have access to that right now, hope I can backfill that tomorrow.