Unmet hours according Ashrae 90.1/2010

I have a question regarding the Unmet Hours required by ASHRAE 90.1/2010. I've always checked the 300 hours parsing only during occupied cooling or heating. However LEED has questioned that the 300 hours must be achieved both during occupied and unoccupied heating and cooling, is this correct?