I am installing chilled water pipes in high raised building. My consultant wants Dain cock

I am installing chilled water pipes in high raised building. My consultant wants Dain cock & Air vent , in every bottle trap Like every ups he require air vent & every down he require drain cock .

chilled water pipe installation Working pressure 5.5 bar , Reason by consultant : To prevent air bubbles .