Energyplus design cooling load is zero
Hello,
I saw someone else asked this question, but they didn't have a thermostat in their zones and that isn't my issue. I have a supermarket with 13 RTUs. One has a design heating load of 0 and 8 have a design cooling load of 0. This surprises me because there is lighting, people, and equipment load in all 9 RTUs that are specifying no load. EnergyPlus still allows me to run the model, so I am able to see that there actually is no heating or cooling energy showing up annually for any of those systems. I tried manually inputting the supply CFM and cooling capacity, but the warning still shows up that there is no cooling load for those rooftop units. Has anyone run into this before?
Thank You, Alisa
Do you have lots of refrigerated cases in your model? They can provide lots of space cooling. Also, check your design day conditions to make sure they are appropriate for your climate.
Do people/equipment/lights/zone control thermostats/cooling and heating SP schedules use SummerDesignDay and WinterDesignDay keywords?
I do have a lot of refrigerated cases in my model, but a lot of the rooftop units that have 0 cooling load do not have any refrigerated case loads, so I don't think that is the issue. Do the SummerDesignDay and WinterDesignDay key words somehow get recognized by EnergyPlus? The lighting for sure has a summer design day schedule of 1 at all time and winter design day has a design day schedule of 0 at all times, which I think makes sense.
Without looking into the input file, few things to first check would be internal loads during summer and winter design days. This warning is generally followed by the message to check Sizing:Zone and ZoneControl:Thermostat inputs. I pulled the RefBldgSuperMarketNew2004_Chicago.idf and commented out SummerDesignDay from the internal loads objects (Equipment/occupancy) and ran it for Chicago weather. It threw the same warning that calculated design cooling load for zone zone is zero. It may not be the same issue in your model but reporting what I found in case that helps.
If the schedules do not specify all day types within a Through period, including SummerDesignDay and WinterDesignDay, then design days will use the AllOtherDays part of the schedule.