Hello everyone

I have a question about the design day in EP+/OpenStudio. I understand for now that the DesignDay is for the general HVAC sizing. If I firstly model a whole building with all passive building systems (without any motorized or mechanical elements), could I run this building simulation without DDY file? Is there any negative impact on this workflow? My intention is to separate the passive building/systems simulation from active features in buildings.

Thanks in advance

Wei

Preview: (hide)

1 Answer

Sort by » oldest newest most voted
3

answered 3 years ago

That is correct. You do not need Design Days to be defined in your model if you have either:

  1. No HVAC system to be autosized in your model,
  2. A hardsized (i.e., user-entered sizing values rather than autosized) HVAC system in your model, or
  3. An autosized HVAC system using an alternative sizing method (e.g., using SizingPeriod:WeatherFileDays).
Preview: (hide)
link

Comments

Thanks Scott for your reply

wei_zhang's avatar wei_zhang  ( 3 years ago )

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

Training Workshops

Careers

Question Tools

1 follower

Stats

Asked: 3 years ago

Seen: 360 times

Last updated: Feb 19 '22