I must perform a leed certification for a proposed building in which there is a hot water circuit connected to a solar collector. How do I have to model it in the baseline building? I have seen that in Table 7.8 there are some indications for electric water heaters but I find nothing about solar collectors.

edit retag flag offensive close merge delete

Comments

What do your solar collectors serve? Is there a backup heater?

Julien Marrec's avatar Julien Marrec  ( 2017-07-31 07:03:33 -0600 )edit

The solar collectors serve the DHW circuit; there is an integrated electric resistance because the solar power is insufficient.

Ricky's avatar Ricky  ( 2017-07-31 07:24:44 -0600 )edit

1 Answer

Sort by ยป oldest newest most voted
1

answered 2017-07-31 08:58:37 -0600

You would model the baseline DHW as having the backup source, so electric heat in your case. And probably with a tank too.

G2.4 and the User's Manual may help. See also this question.

edit flag offensive delete link more

Comments

1

Everything is clear. Thank you for the answer and the link to the other question, they were both useful.

Ricky's avatar Ricky  ( 2017-07-31 10:15:52 -0600 )edit

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

Training Workshops

Careers

Question Tools

1 follower

Stats

Asked: 2017-07-31 06:16:19 -0600

Seen: 176 times

Last updated: Jul 31 '17