CHP + Absorption Chiller

asked 2016-11-03 11:17:38 -0500

AndreTarta gravatar image

updated 2016-11-12 03:20:01 -0500

I completed a model using the following element (and all the related objects):

  1. One AirTerminal:SingleDuct:VAV:HeatandCool:Reheat
  2. Boiler:HotWater
  3. Chiller:Electric:EIR
  4. CoolingTower:TwoSpeed
  5. WaterHeater:Mixed

The model run correctly and this is the basic case, now I want to implement a model that use a Internal Combustion Engine and an Absorption Chiller to cover the basic load. I will resize the Boiler and the Chiller to cover the peak load.

I completed the model with CHP and Absorption Chiller but I have a problem: the CHP always work at 100% and if I size it in a way that it cannot work at 100% for all the time the simulation fail (error on maximum temperature over the limit in the hot water loop).

Any idea on what I can do to fix this problem?

Thank you!

Andrea

edit retag flag offensive close merge delete

Comments

What control method are you using for the CHP engine?

Archmage gravatar image Archmage  ( 2016-11-14 16:13:51 -0500 )edit

I am using FollowThermal

AndreTarta gravatar image AndreTarta  ( 2016-11-14 16:35:13 -0500 )edit

1 Answer

Sort by ยป oldest newest most voted
0

answered 2016-11-30 04:19:04 -0500

AndreTarta gravatar image

I correctly modeled the system, but the Absorption Chiller don't work to cover the basic load as I indicate in the PlantEquipmentList (first listed). There is a way to impose that the Absorption Chiller must work to cover the basic load?

edit flag offensive delete link more

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

 

Question Tools

1 follower

Stats

Asked: 2016-11-03 11:17:38 -0500

Seen: 272 times

Last updated: Nov 30 '16