DHW is on the waterside tab. DHW loads are created as direct process loads on a DHW loop. You can create up to 10 different process loads on a loop - each with its own peak flow rate and schedule.
Alternately, you could create secondary DHW loops under the primary DHW loop with their own process loads that would be summed up and served by the primary loop. The only advantage I see to this is you would have an annual PS-D entry and PS-H report showing monthly usage of individual loops.