In the IDF Editor, under ZoneHVAC:Equipement List, you can change the sequence manually by setting up the Zone Equipment Cooling Sequence and Zone Equipment Heating or No-Load Sequence.

"Equipment is simulated in the order specified by Zone Equipment Cooling Sequence and Zone Equipment Heating or No-Load Sequence, depending on the thermostat request. For equipment of similar type, assign sequence 1 to the first system intended to serve that type of load. For situations where one or more equipment types has limited capacity or limited control, order the sequence so that the most controllable piece of equipment runs last. ;"