Thanks for the response! I should probably clarify-when I am saying "acceptable range" for the storage room, I don't mean thermostat set point. I mean that, in the example I gave, when the open office thermostat is satisfied and has no UMLH, having the storage room be within 60-80 as a byproduct (since the control is in the open office) would be ok and shouldn't be considered an UMLH for the storage room.

From my understanding of 90.1, a non-master-room being outside of the zone setpoints shouldn't be an UMLH if it is within an acceptable design range. Is that correct?