Hi All,
I accidently set a multiple setpoint managers in EnergyPlus. (SetpointManager:OutdoorAirReset, SetpointManager:Scheduled:DualSetpoint) The SPM I need is SetpointManager:Scheduled:DualSetpoint, not SetpointManager:OutdoorAirReset)
I understand from the reference that the one that comes later in IDF (which is SetpointManager:OutdoorAirReset in this case) overwrites the previous one.
But I set the plant loop demand calculation scheme to be 'DualSetpointDeadband', and in this regard, the simulation terminates without SetpointManager:Scheduled:DualSetpoint.
In this case, I wonder if this would enable SetpointManager:Scheduled:DualSetpoint, not SetpointManager:OutdoorAirReset. If not, I have to go through a massive work to make up for the accident. So, I sincerely request for your anwsers. Thank you.