Weekdays and weekend schedule simulation on EnergyPlus

Hello,

I'm working on a ptojet to simulate a simple house. But I want to do an schedule of occupation for weekdays and for weekend. The problem is that I'm not sure how to do properly. I know that is a very simple question but I'm new user of E+. Can you help me please? This is what I did. I know that is wrong or It is not working well.

Schedule:Compact, Sch_OcupSala, !- Name SchLim_Fracao, !- Schedule Type Limits Name Through: 12/31, !- Field 1 For: Weekdays, !- Field 2 Until: 7:00, !- Field 3 0, !- Field 4 Until: 21:00, !- Field 5 .5, !- Field 6 Until: 22:00, !- Field 7 1, !- Field 8 Until: 24:00, !- Field 9 0, !- Field 10 For: Weekend, !- Field 11 Until: 9:00, !- Field 12 0, !- Field 13 Until: 11:00, !- Field 14 .5, !- Field 15 Until: 22:00, !- Field 16 1, !- Field 17 Until: 24:00, !- Field 18 0; !- Field 19

I need to simulate with different people occupation on weekdays (Monday to Friday) and weekend (Saturday and Sunday). But I'm not sure that I'm doing that in the correct Objet >> Schedule:Compact

Thanks!

Weekdays and weekend schedule simulation on EnergyPlus

Hello,

I'm working on a ptojet project to simulate a simple house. But I want to do an schedule of occupation for weekdays and for weekend. The problem is that I'm not sure how to do properly. I know that is a very simple question but I'm new user of E+. Can you help me please? This is what I did. I know that is wrong or It is not working well.

Schedule:Compact,
    Sch_OcupSala,            !- Name
    SchLim_Fracao,           !- Schedule Type Limits Name
    Through: 12/31,          !- Field 1
    For: Weekdays,           !- Field 2
    Until: 7:00,             !- Field 3
    0,                       !- Field 4
    Until: 21:00,            !- Field 5
    .5,                      !- Field 6
    Until: 22:00,            !- Field 7
    1,                       !- Field 8
    Until: 24:00,            !- Field 9
    0,                       !- Field 10
    For: Weekend,            !- Field 11
    Until: 9:00,             !- Field 12
    0,                       !- Field 13
    Until: 11:00,            !- Field 14
    .5,                      !- Field 15
    Until: 22:00,            !- Field 16
    1,                       !- Field 17
    Until: 24:00,            !- Field 18
    0;                       !- Field 19

19

I need to simulate with different people occupation on weekdays (Monday to Friday) and weekend (Saturday and Sunday). But I'm not sure that I'm doing that in the correct Objet Object >> Schedule:Compact

Thanks! Thanks!

Weekdays and weekend schedule simulation on EnergyPlus

Hello,

I'm working on a project to simulate a simple house. But I want to do an schedule of occupation for weekdays and for weekend. The problem is that I'm not sure how to do properly. I know that is a very simple question but I'm new user of E+. Can you help me please? This is what I did. I know that is wrong or It is not working well.

Schedule:Compact,
    Sch_OcupSala,            !- Name
    SchLim_Fracao,           !- Schedule Type Limits Name
    Through: 12/31,          !- Field 1
    For: Weekdays,           !- Field 2
    Until: 7:00,             !- Field 3
    0,                       !- Field 4
    Until: 21:00,            !- Field 5
    .5,                      !- Field 6
    Until: 22:00,            !- Field 7
    1,                       !- Field 8
    Until: 24:00,            !- Field 9
    0,                       !- Field 10
    For: Weekend,            !- Field 11
    Until: 9:00,             !- Field 12
    0,                       !- Field 13
    Until: 11:00,            !- Field 14
    .5,                      !- Field 15
    Until: 22:00,            !- Field 16
    1,                       !- Field 17
    Until: 24:00,            !- Field 18
    0;                       !- Field 19

I need to simulate with different people occupation on weekdays (Monday to Friday) and weekend (Saturday and Sunday). But I'm not sure that I'm doing that in the correct Object >> Schedule:Compact

Thanks!