Chiller sequencing

In case of having multiple chillers in parallel in chilled water plant loop, some simple control strategy could be considered:

Uniform *: In this control strategy, each chiller would make same load part. *Sequencing: In this control strategy, the first chiller would work at its highest PLR and then the other chiller and the other and...

Currently, I am working with OpenStudio. I chilled water loop tab, there is a part for controlling. An availability manager part can be seen but, I don't know how to use it and I don't know if it's capable of preforming mentioned control strategies.

1- Can anyone help me with this?

2- I have another question related to this. Is it possible in each timestep we determine how many chillers to use and what control strategy to use?

Chiller sequencing

In case of having multiple chillers in parallel in chilled water plant loop, some simple control strategy could be considered:

Uniform *: Uniform: In this control strategy, each chiller would make same load part. *Sequencing: In this control strategy, the first chiller would work at its highest PLR and then the other chiller and the other and...

Currently, I am working with OpenStudio. I chilled water loop tab, there is a part for controlling. An availability manager part can be seen but, I don't know how to use it and I don't know if it's capable of preforming mentioned control strategies.

1- Can anyone help me with this?

2- I have another question related to this. Is it possible in each timestep we determine how many chillers to use and what control strategy to use?

Chiller sequencing

In case of having multiple chillers in parallel in chilled water plant loop, some simple control strategy could be considered:

Uniform: In this control strategy, each chiller would make same load part. Sequencing: In this control strategy, the first chiller would work at its highest PLR and then the other chiller and the other and...

Currently, I am working with OpenStudio. I chilled water loop tab, there is a part for controlling. An availability manager part can be seen but, I don't know how to use it and I don't know if it's capable of preforming mentioned control strategies.

1- Can anyone help me with this?

2- I have another question related to this. Is it possible in each timestep we determine how many chillers to use and what control strategy to use?