Question-and-Answer Resource for the Building Energy Modeling Community
Get started with the Help page
Ask Your Question
2

CBECC-Com occupancy and lighting schedules

asked 2014-11-04 18:40:10 -0500

NORESCO's avatar

updated 2015-01-09 12:02:47 -0500

When I created occupancy and lighting schedules for my project, I entered them in the space data screens, but they are not being used for my compliance analysis. How can I fix this?

edit retag flag offensive close merge delete

1 Answer

Sort by ยป oldest newest most voted
2

answered 2014-11-05 11:33:19 -0500

cbecc's avatar

For a compliance analysis, all schedules used are defined by the ACM. Any schedules defined or assigned by the user will be ignored. User schedules will only be used when the software is run in research mode.

edit flag offensive delete link more

Comments

The compliance software includes equipment schedules for Title 24 correct? Are there any schedules that the user is expected to define for Title 24?

macumber's avatar macumber  ( 2014-11-06 09:58:01 -0500 )edit

No- there are no schedules that the user is expected to or even allowed to define in the Title 24 performance model.

Anna Osborne Brannon's avatar Anna Osborne Brannon  ( 2015-12-11 18:44:28 -0500 )edit

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

Careers

Question Tools

1 follower

Stats

Asked: 2014-11-04 18:40:10 -0500

Seen: 232 times

Last updated: Nov 05 '14