For example, In January month we want to set the occupancy to 100 people while 200 people for February and so on. Some general approach applicable to various other parameters also would help.

Preview: (hide)

1 Answer

Sort by » oldest newest most voted
1

answered 4 years ago

santle's avatar

In schedule-compact- month-wise, day-wise, and hour-wise scheduling of people, setpoint temperature and so on can be configured.