people count differences

asked 2018-11-13 01:50:55 -0600

Philip Caesar Ebit's avatar

updated 2018-11-13 10:17:56 -0600

Hi all, i would like ask someone to help me with this problem. I scheduled 38 persons from 7:30 to 9:00 am, but when I see the results of the zone people count I observed that the result start from 6:31 instead of 7:30 (see images below) and I don't know how this happen. I would like to know what is the reason for this and how can I fix this.

Thank you and your help is much appreciated.

image description image description

edit retag flag offensive close merge delete

Comments

Are you applying Daylight Savings Time (DST)? This is an input field of the RunPeriod object.

Aaron Boranian's avatar Aaron Boranian  ( 2018-11-13 14:57:48 -0600 )edit

1 Answer

Sort by ยป oldest newest most voted
3

answered 2018-11-16 16:46:35 -0600

Fairly certain that @Aaron Boranian has pointed out the reason. EnergyPlus always reports time series output using standard time. When daylight savings time (DST) is active, all scheduled values will shift up an hour.

edit flag offensive delete link more

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

Training Workshops

Careers

Question Tools

1 follower

Stats

Asked: 2018-11-13 01:50:55 -0600

Seen: 331 times

Last updated: Nov 16 '18