Most common issues with applying baseline building measure

asked 2016-11-15 12:36:39 -0600

willyJohan's avatar

updated 2016-11-15 15:38:43 -0600

Does anyone have experience using the "Create Baseline Building" measure in developing Appendix G models?

If so, which areas should be one's primary focus for QA/QC of the resulting models? And, more specifically, in which ways is this measure most likely to result in a baseline that is showing higher energy consumption than a proper, manually developed, baseline model?

Considering making the transition to using OpenStudio for LEED compliance modeling and would love to hear folks' thoughts on potential pitfalls of this approach.

Thanks.

edit retag flag offensive close merge delete

Comments

I think you mean the "Create Performance Rating Method Baseline Building" Measure in the same gem.

__AmirRoth__'s avatar __AmirRoth__  ( 2016-11-15 12:57:58 -0600 )edit

Well, that did not take long to plumb the depths of my knowledge. I am using this measure, are we talking about the same thing?

willyJohan's avatar willyJohan  ( 2016-11-15 13:22:36 -0600 )edit

Issue #1: having multiple versions of the same measure floating about and expecting users to install custom ruby gems

Lyle K's avatar Lyle K  ( 2016-11-15 17:29:29 -0600 )edit

I am starting to be concerned that my ignorance of what exactly a gem does will keep me from properly using this (or any other) measure. In general is this the case?

willyJohan's avatar willyJohan  ( 2016-11-15 18:01:03 -0600 )edit
2

Let me clear up some things:

  1. This is the measure: Create Baseline Building
  2. You don't have to install any gems to use it. See this YouTube video.
aparker's avatar aparker  ( 2016-11-16 09:35:50 -0600 )edit