I need to know the annual energy consumption of a building (lights, computers, HVAC) in TRNSYS. Anyone knows what output should I put in TRNBUILD??

edit retag flag offensive close merge delete

2 Answers

Sort by ยป oldest newest most voted
6

answered 2016-06-20 15:45:40 -0500

Tim McDowell's avatar

Because of the inherent flexibility of TRNSYS, this is not a straight-forward process and depends on what you are looking for in the energy consumption of the building. Gains from lighting and equipment are specified in the building model (Type56) either by specifying the schedules and rates inside of the building model using TRNBUILD or set as inputs and then specified outside of the building model using other components in the TRNSYS project. If you are specifying the gains inside of the building model you can use the balance output 958 for the total internal gains for a zone. If you are specifying the gains using other components in your project you can use the standard integrator and printer components to get the energy consumption. For an HVAC system, you can specify ideal heating and cooling systems inside the building component that calculate the amount of energy that needs to be added or removed from zone to maintain a setpoint. These energies can be output from the building model using multiple different outputs including QSENS, QLATD, QHEAT, QCOOL, etc. However this is energy input to the zone and not the energy consumption by an HVAC system. To determine the energy consumption of an HVAC system, you will need to include an HVAC system in your TRNSYS project.

edit flag offensive delete link more
0

answered 2019-03-08 06:31:03 -0500

Saro56's avatar

Better late than never, I hope it may be useful to someone. I think that, after selected the suitable outputs from a deck component, to obtain the annual (cumulated) value of a quantity you have to add each timestep contribution by mean of TYPE24 (integrator) and then to pass the result to an output component like TYPE25. The same may be probably done by mean of TYPE55 (periodic integrator) but I never did it.

edit flag offensive delete link more

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

Careers

Question Tools

1 follower

Stats

Asked: 2016-06-16 15:11:52 -0500

Seen: 775 times

Last updated: Jun 20 '16