@sborle Your sample method is set to individual_variables which only lets one variable change at a time, with all other variables using the static variable value. I'm not sure where the 33 runs are from vs. 20 (19 variable values plus baseline - all static values). If you change the sample method to all_variables you should have more datapoints, with all variables being altered for each datapoint. However 446*5 equals 480 so you still won't get 1000 runs, but it doesn't hurt to list a larger number of samples than possible. If you made your variables continuous instead of discrete, then you would get 1000 datapoints.