See Section 1.2.1 in https://energyplus.net/sites/all/modules/custom/nrel_custom/pdfs/pdfs_v8.7.0/ExternalInterfacesApplicationGuide.pdf

A more in-depth discussion why this time delay is needed for E+ coupling is described in http://dx.doi.org/10.1080/19401493.2013.808265 in particular Section 7.