Question-and-Answer Resource for the Building Energy Modeling Community
Get started with the Help page
Ask Your Question

Revision history [back]

click to hide/show revision 1
initial version

I have had this issue before as well. From what I understand, OpenStudio counts on converting the EnergyPlus results from SI to IP. My guess is you are running the measure "Set Output Table to IP Units." If you delete that measure, the OpenStudio results should work.

There is a little more explanation from David Goldwasser here: https://unmethours.com/question/20371/openstudio-results-monthly-overview-demand-only/.