Question-and-Answer Resource for the Building Energy Modeling Community
Get started with the Help page
Ask Your Question

Revision history [back]

click to hide/show revision 1
initial version

I have not experienced this case in E+, I'm IESVE user. But I think the concept for getting this done is the same. As usual with double skin facade, I model cavity zones as thermal zones, separated them as individual thermal zone at each floor, cavities are connected vertically. In case I realize this for study, I separate them to 2 or even 4 at each floor to see roughly how the temperature gradient inside the cavity. Then using air net work on IESVE to connect them all and connect to AHU. Hope this can help.