The Hospital reference building model has some bad schedules that don't zero out lights and equipment for winter design days. This causes the heating loads to be zero and the reheat coils to have zero capacity for some zones. Because there is no heating capacity for those zones, the temperatures are floating well below the setpoint throwing off the predicted load.
2 | No.2 Revision |
The Hospital reference building model has some bad schedules that don't zero out lights and equipment for winter design days. This causes the heating loads to be zero and the reheat coils to have zero capacity for some zones. Because there is no heating capacity for those zones, the temperatures are floating well below the setpoint and throwing off the predicted load.